2015 Annual Meeting Report

2015 Annual dinner

Impressive amount of volunteers last year.

  • 3560 Volunteer Hours
  • 4708 VYCC plus Volunteer Hours
  • 68 Work days from the end of April to the end of October
  • 840 Number of volunteers in the park in 2014
  • Thank you very much to everyone who has helped in the park.

 

Projects Completed in 2014:

• Widened pedestrian bridges with Rutland Rotary South
• Rerouted Annex
• Trillium rerouted
• Santa’s Little Helper Mud holes repaired
• Lower Giorgetti by old softball field improved RHS XC team
• Two kiosks for Carriage Trail
• Repaired fabric showing on Underdog powerline
• Installed 7 French Drains on Birches near Voldemort
• First Turn on Exit Strategy had more dirt added to it
• Small reroute on PA4J/Lonely Rock has a less abrupt turn now
• VYCC 3 weeks on Carriage Trail
• VYCC 3 weeks in the fall on Carriage Trail and in the park for a total of 6 weeks
• Ribbon cutting for Carriage Trail
• Repaired powerline on Strong Angel
• Repaired powerline on Jersey Turnpike
• French Drain installed at base of powerline on Jersey Turnpike   near Arthur’s Chair
• French Drain installed on Lonely Rock

 

Future Projects for 2015 and beyond:

• Sore Elbow Segment 2
• Sore Elbow Segment 3
• Furlough needs TLC to prevent water running straight down it
• Shimmer needs TLC on corner to prevent trail erosion
• ‘S’ turn on PA4J near Stegosaurus needs some TLC
• Ramp VYCC started to build off PA4J to enter Strong Angel from West side needs attention
• Reroute for Santa’s near the Droopy Muffin intersection
• Boardwalk at main entrance needs to be leveled
A suggestion was made to widen the boardwalk
A suggestion of taking part of the white pine down that   hangs over the boardwalk that the pileated woodpecker is working over
• Broken Handlebar Extension-anyone will to step up and help with this trail?
• Trail by Carving Bench to prevent people from walking over gardens
• Front entrance-smooth upper tier out so can be mowed
• Fabric on Overlook near the top of Root Ride

Introduced the redesigned Pine Hill Park webpage www.pinehillpartnership.org   Check it out.

We need a champion to drive the Broken Handlebar Trail Extension project

We would like to extend our gratitude to Tim Vile and Ben Reller who have helped us out in many way over the years.

Our board of directors for 2015 are: Joel Blumenthal, Andy Shinn, Keith Wight, Shelley Lutz, Claus Bartenstein, Dave Jenne and Bruce Saxman.

Please use TrailHub.org to find out condition of trails.